 is optimal from the point of view of strength. This implies a twofold 

increase in the depth of the keys while maintaining their existing height or an increase 
in the depth to 30 mm while reducing the height to 120 mm, for example, for the 
PVL 80. 

                 

 

                                    а)                                                                             б) 

Figure 1. The joint of three-layer wall panels on flexible loops: 

a) horizontal projection; b) external appearance of the loop; 1 ‒ outer layer;  

2 ‒ base layer; 3 ‒ wire rope loops; 4 ‒ vertical mortar joint;  

5 ‒ longitudinal reinforcing bar; 6 ‒ key 

 
Another direction of modernization of large-panel housing construction is the use 

of a wide step of bearing structures, which makes it possible at the design stage to vary 
a set of apartments on typical floors without changing the structural design of the 
building, and at the operation stage to perform re-planning inside the apartments as part 
of its structural cell. 

Overlapping in buildings with wide wall spacing are projected from pre-stressed 

hollow-core slabs. At the same time, for traditional platform joints in the support zone 
of the walls, there is the problem of ensuring strength and the use of additional 
structural measures is required. No formwork hollow-core slabs are modern low-cost, 
high-tech structures of hollow core flooring. However, unlike serial hollow-core slabs, 
the no formwork slabs do not have upper longitudinal structural reinforcement and 
embedded parts for connection with other prefabricated structures. 

In experimental studies [10], the formation of cracks normal to the longitudinal 

axis near supports of no formwork hollow-core slabs in the area of the platform joint 
is observed, which is not allowed by the standards and requires the installation of upper 
structural reinforcement. There are proposals [11] to strengthen the support zone of 
slabs, implemented either in the process of their manufacture, or at the construction 
site. 

Based on the reliability of the joint and the ease of buildings erection, the most 

rational is considered to be a combined joint of wall panels and floor slabs. Contact-